Internal Sync
Gemma-internal delivery planning for the ROTOP project, off the ClickUp board. Bijan, Bianca, and Christophe, who carries the bulk of the build.
Topics
- Requirements for Sales and Finance (what has been discussed so far), the data dumps, and QA checks.
- Charge-day split: Bijan 4.5 (remaining days as buffer for other topics), Christophe 13, Bianca 2.5, plus a 2-day buffer.
- Internal ETA: mid-August (Gantt chart in the proposal).
Effort estimate
| Workstream | Est. days | Owner |
|---|---|---|
| Infrastructure setup | 2.0 | Bijan |
| Data ingestion (BC + Sage) | 2.5 | Bijan |
| dbt base layer | 2.5 | Christophe |
| dbt transformation layer | 5.5 | Christophe |
| MetricFlow semantic layer | 4.0 | Christophe |
| Claude Cowork integration | 1.0 | Christophe |
| Project management & workshops | 2.5 | Bianca |
| Buffer | 2.0 | tbd |
| Total | 22 days |
Working language
Main language German. For Christophe: written German too, spoken English is fine and aligned with Torsten.